Treatment activity :
Head-end facilities are on a shutdown period for maintenance. From all treated assemblies, a total of 526.12 tons have been processed to date this year.

The actuality, it is also... Works of disassembling, in the zone of the marling, of the old pipe of liquid releases are in progress accordance with the program.
The results of analyses of the samples performed in accordance with the specific environmental monotoring program of the site are all lower than 1 Bq/g.