Weekly report : from November, 16th to 22th 2006.

11/23/2006
Press release

Treatment activity:
 
During this period, the UP2 800 and UP3 plants treated 38 tons of spent fuel. From all treated assemblies, a total of 850 tons have been processed to date this year.

During this period, 25 canisters of vitrified fission products has been produced(1) in the vitrification facilities. Since the beginning of the year, 879 canisters have been produced.

The facility of hulls compaction (ACC) produced 33 canisters of compacted residues. Since the beginning of the year, 1219 canisters have been produced.

The actuality, it is also...

... treatment of all used Dutch fuel
On November 17, the UP3 plant began a treatment run involving 28 used fuel elements owned by Dutch utility EPZ. As of November 23, all of EPZ's used fuel at the plant, i.e. 8.94 metric tons, had been sheared. The run falls under the contract amendment signed by AREVA and the Dutch utility in 1993 and pertains chiefly to the used fuel received in December 2005.
 


(1)The fission products (ultimate residues of spent fuel) are incorporated in heated glass to approximately 1100°C. The whole is poured in stainless steel containers. The fission products are an integral part of stable, compact and resistant glass. This process is called vitrification.