At the UP2 plant, shearing of fuel assemblies from a batch of 1300 MWe EDF fuel is in progress in the R1 head-end facility.
A total of 698 metric tons of uranium have been processed to date this year.
At the R7 vitrification facility, lines A and C are in service, line B is on standby.
A total of 424 canisters of glass have been produced to date this year.
At the UP3 plant, the T1 head-end facility is on standby for monitoring operations.
The 13th of November, the end of shearing operations realised on the batch T109 BWR ISAR1, indicated the achievement of the realisation of the program 2000.
A total of 387 metric tons of uranium have been processed to date this year.
At the T7 vitrification facility, lines A and B are in service, line C is on standby.
A total of 262 canisters of glass have been produced to date this year.