Treatment activity:
During this period, the Establishment treated 81,75 tons of spent fuel assemblies from EDF power plants.
From all treated assemblies, a total of 592,65 tons have been processed to date this year.
During this period, 26 canisters of vitrified fission products have been produced(1).
Since the beginning of the year, 264 canisters have been produced.
It should be noted that the facility of hulls compaction (ACC) produced 65 canister of compacted residues.
Since the beginning of the year, 447 canisters have been produced.
(1)The fission products (ultimate residues of spent fuel) are incorporated in heated glass to approximately 1100°C. The whole is poured in stainless steel containers. The fission products are an integral part of stable, compact and resistant glass. This process is called vitrification.