Weekly report : from July 12 through July 18, 2001

7/19/2001
Press release

UP2 plant :
At the UP2 plant, R1 head-end facility is on shutdown period for maintenance.
A total of 332 metric tons of uranium have been processed to date this year.

At the R7 vitrification facility, lines A and B are on standby, line C is in service.
A total of 234 canisters of glass have been produced to date this year.

UP3 plant :
At the UP3 plant, T1 head-end facility is on a shutdown period for maintenance.
A total of 51 metric tons of uranium have been processed to date this year.

At the T7 vitrification facility, lines A, B and C are on standby.
A total of 146 canisters of glass have been produced to date this year.