Report from January 1st to 16th, 2012

1/17/2012

A campaign of treatment of EDF spent fuels started again on January 15th in one of both plants. Other plant is in the shutdown for scheduled maintenance.

  • During this period, 17 containers of vitrified waste were elaborated in vitrification facilities.
  • 20 containers of compacted waste were elaborated in the facility of compaction of hulls, which assures the packaging of the metallic structures of spent fuels.
Contact presse AREVA
Contact presse AREVA

Transports
Julien Duperray
T : 01 34 96 04 18
P : 06 86 15 41 95
julien.duperray@areva.com


AREVA la Hague
Maryline Breton
T : 02 33 02 75 02
P : 06 08 03 00 03
maryline.breton@areva.com

Attachée de Presse
Marie Dudouit
T : 02 33 02 79 93
P : 06 79 91 40 54
marie.dudouit@areva.com